NGD. The Lift & Shift Specialists

NGD’s Lift & Shift process is unmatched in the industry, and follows these steps;

  • Elegant shutdown of all equipment
  • De-rack all equipment and pack in flight cases
  • Sign off contents and seal all flight cases, ensuring electrical safety
  • Transport all equipment and racks to NGD
  • Offload racks and unpack all flight cases at the target data hall
  • Confirm contents and condition of equipment unchanged
  • Re-rack equipment, reconnect and power on
  • Run and sign-off connectivity tests
  • Confirm application availability and confirm data integrity